The Klickitat County News, Goldendale, WA., June 20, 1935, page 12
WILL FURNISH "GIANT" POWER
P.P.&L. Company Furnish Power for 200 Ton Sand Shovel
Electric shovels served by Pacific Power will take out
1,000,000 tons of gravel from a Columbia river bar near Avery for the Bonneville
dam, according to B.P. Bailey industrial engineer.
Operations on the job of moving the gravel out of the
bar to the dam site are now underway, following the completion of two and
one-half miles of transmission line from Wishram to serve the Avery plant.
In 16 days, the two and one-half miles of line was surveyed,
right-of-way purchased, and the line finished and ready for operation.
Columbia Construction Company, which has the contract
for the main spillway dam, will receive its supply of gravel from this plant
and its sand from a hill near Bingen. The large gravel bar at Avery, submerged
during high water, is more than 30 feet deep. The gravel is clean and can
be handled easily.
Work was begun May 8 on the new transmission line, which
connects with The Dalles-Goldendale line. G.R. Johnson, chief of the survey
crew of four men, conducted the survey, C.O. Bunnell had charge of purchasing
right-of-way. A line crew from The Dalles under the supervision of Frank
Jahn, foreman, built the line, and the crew from the construction department
under the supervision of Lance Read, foreman, built the sub-station at Avery.
Fifty-seven polls from 35 to 45 feet high where required
for construction. A bank of three 200-kva transformers were installed at
Avery to step down the energy from 11,000 to 2300 volts. And oil circuit
breaker was installed on the 2300-volt line to control the load. Total cost
of the line was $8500.
Estimated load at the plant will be 250-kw. Most of it
will be used for the shovels, which will operate for the next two years.
It is estimated that 500,000 tons of sand will be taken
out of the hill at the Bingen by drag lines for the main spillway dam. Work
will start on the main dam as soon as the high water subsides.
A steam derrick with large bucket for loading will be
used in the loading operations, it was pointed out. The derrick has a 90
foot boom and a 5-yard scoop. The equipment weighs over 200 tons and was
formerly employed at the Boulder dam.
[HOME]
© Jeffrey L. Elmer