Search billions of records on Ancestry.com

The Hood River Glacier, Hood River, OR., September 26, 1907, page 1

PROGRESS MADE ON NORTH BANK
Rails Being Laid At Both Ends
Passenger Trains Will Be Put On Soon To Connect With Boat Lines of Company

     It is expected that the North Bank road will be completed as far as Lyle by October 15, and that passenger trains will be put on to connect with the boat line at that place as soon as the rails are  laid.  This is the opinion of A.W. Zimmerman, agent for the North Bank and regulator line at The Dalles, who was in the Hood River Saturday.  Mr. Zimmerman said that track laying has proceeded close to The Dalles, and was being pushed with a big force.  There are still some rock cuts to be made the other side of Lyle, but that will not delay the work, as the track will be laid around bad places on the old grade, and used as temporary track.  Fourteen crews are now engaged in running construction trains between Cliffs and Pasco, although no regular freight schedule is yet maintained.  The road is being ballasted as fast as the rails are laid, and is ready for business.
     Track laying will be started at Vancouver the first of the month and the grade is finished as far as Cape Horn, so that trains will be run out of Vancouver as fast as the track is laid.  The road will be double tracked at once as far as the Cape Horn tunnel, and until the road is completed between Lyle and the big tunnel, transfers between these points will be made by boat.  It is probable that a free ferry will be put in at The Dalles and at Hood River, to be run in connection with the passenger service, as passengers traffic at these two places will be worth going after.
     It is the intention of making the running time two hours between the station opposite The Dalles and Portland, in which case the road will get many passengers from the Oregon side.  While the O.R. & N. is improving its road a great deal, and will be able to reduce its running time from, yet the North Bank will have a much
straighter track and be able to make better time, in the opinion of railroad men, as the road has been built with that end in view from the start.
     But whether the road is finished November 15 or May 1, no one has had an opportunity to make a close inspection of the engineering problems which have been accomplished will accuse either contractors or engineers of loafing on the job, and the completeness and thoroughness of the work is the admiration of the initiated and the novice as well.  In fact it is probably the only railroad that has been built in this country on which the grade will be absolutely complete when a train schedule is put in operation over it and which will allow a speed of 60 miles an hour from the start, if its management sees fit to run trains at that rate, and they say they will.  This is accounted for by the fact that on the whole line there is not a curve of over three degrees; that all projections, either on grade or overhead, that would in any way jeopardize the safety of trains have been removed, in many instances at an expenditure of thousands of dollars not included in the original contract; that there is no grade on the line of over 10 feet to the mile (about 2 inches to the hundred feet) and that the roadbed is being constructed with a solidity that will make it an almost perfect grade from the time the rails are laid.
     Running through Lyle there is a two- mile stretch that will require considerable work in addition to a bridge which is being built over the Klickitat river.  A mile below this is one of the most expensive bits of construction on the line.  Here in a distance of a mile are four tunnels.  They have cost the new road $300,000, exclusive of the track laying, and are not finished yet, although trains could be run through three of them if necessary.  At the west end of the stretch a steam scraper is at work removing thousands of cubic yards of sand that for many months baffled the engineers and resulted in the death of one man and seriously injured four more.  The configuration of the ground is of such a nature that steam shovels cannot be used, owing to the fact that the sand crowds down on the shovel and chokes it and it is now be removed by scraping off the top and going down to grade gradually.  Workmen are at the present concreting this series of tunnels.
     All tunnels on the new road will be concreted, with the exception of the one at Cape Horn, which is over 4000 feet long -- the longest on the road, the rock in it being of a nature that is considered safe without the use of concrete.  The tunnels are 16 feet wide by 24 feet high and when finished will be faced with substantial portals.  At the east end of this series of tunnels is the longest trestle on the road -- 100 feet over a mile -- and said by contractors to have been built to stand a speed strain of 60 miles an hour.
     Opposite Memaloose Island is to be found and uncompleted section of grade through which runs a culvert 12 feet in diameter.  It is the outlet for a creek which it is expected to use for fluming lumber down from a timber belt back from the river.  Like all the under crossings and culverts along the new road, it is built of solid concrete, and is one of the permanent pieces of work, not usually put in on the first construction of a railroad.  Directly below this, considerable rock work remains to be completed, one section of which is still to be blasted out, which will require several months’ work.  It is located near what will be one of the most spectacular points on the road, huge rocks rearing themselves alongside the grade toward the river, affording a site similar to the Pillars of Hercules and consisting of four instead of two great masses of stone, apparently up-ended.  Below this is a long fill, the piles for which it is evident that there is still much work.  Approaching Bingen, the grade is completed.  The mountain of rock opposite Mosier, which was blown into the river last winter, has received additional attention since, having been cut away many feet back from the grade to prevent ice formations from dropping on it and presents the appearance of a huge wall hundreds of feet in height, which has been gone over by a stonecutter with a gigantic cutting tool.  Along here is said by the chief engineer of the road to be the best finished piece of grade on the whole line of the new road.  Below this the grade is completed to the White Salmon river.  The bridge of the former remains, however, to be built.  Work was completed on it early last spring, but high water in the Columbia flooded the excavations and for the abutments, and it is not lowered sufficiently to allow operations to be resumed. Engineers say it that it will not, however, interfere with the running of the trains, as piling can be driven and temporary structure made to allow of their crossing.
     From Underwood to Drano, a distance of seven miles, work is being pushed rapidly, but there are a number of uncompleted pieces of grade, in addition to work on the four tunnels.  The tunnels are bored, and are now being concreted, and are in about the same stage of completion as those situated on the upper end of the division near Lyle.  At Drano a trestle nearly a mile in length is ready to be finished.  Work on it was only commenced recently, and is not expected to be finished before cold weather sets in.  A bridge over the Llittle White Salmon river must also be built on this section.  Fills, small pieces of grade and gaps of various descriptions yet remain to be connected up between Drano and the eastern end of the Cape Horn tunnel.  Below Stevenson and opposite Cascade Locks there is still considerable uncompleted grade.  Seven miles above Stevenson the bridge over Wind river is also one of the pieces of construction that remains unfinished.  It is not believed by contractors that this long stretch of uncompleted grade from Lyle to Cape Horn can be finished sufficiently to allow trains to be run over it by November 1.
     The unusual width of the grade of the new road has been the cause of much speculation by railroad men and others who have wondered why so much expense was being entailed for a single track road when a narrower road would have answered the purpose.  This is now explained by the fact that it was the original original intention to double-track the road except on bridge and in tunnels.  This order was afterward modified to double-track 20 miles out of Kennewick and from Vancouver to the west end of the Cape Horn tunnel which will be done as soon as the road is in operation.  The great expense at which the road road has been built from Kennewick to Portland estimated at $10,000,000, is said to be justified when it is taken into consideration that the Portland & Seattle will virtually be the outlet to Portland of both the Northern Pacific and Great Northern for all through freight in addition to picking up a good big local business from the grain country of Eastern Washington and points along the line, which are expected to develop lumber and other industries, and the level road, which has been built to be operated at all seasons of the year, avoiding that heavy snow-fall and grades on the mountain divisions of the Northern Pacific.  Floods in the Columbia River have also been taken into consideration, is evidenced by the fact that the grade of the Portland & Seattle is placed eight feet above the high water of 1894, the highest ever known.
     It is said too, it will be more economical to haul freight for points on the Northern Pacific between Portland and Tacoma over the new road than over the mountain division of the Northern Pacific, and that it is expected to use it for that purpose when completed.  By using the Portland & Seattle the Northern Pacific and Great Northern through freight for Portland will save a haul of approximately 153 miles.  It will be shorter, and easier and quicker to haul it over this route from Spokane to Tacoma then it is over for the one in use at present from Spokane to Portland.
     A comparative distance over the two routes as completed approximately by the engineers of the Portland & Seattle is as follows:

Over Northern Pacific.

                                                            Miles

Spokane to Pasco                                146
Pasco to Ellensburg                             127
Ellensburg to Auburn                           105½
Auburn to Tacoma                              18
Tacome to Portland                             145½

Total                                                    542

 

Over Portland & Seattle

                                                            Miles

Spokane to Pasco                                145½
Pasco to Kennewick                            2½
Kennewick to Portland                        241

Total                                                    389

 

Spokane to Portland,  Distance Saved

Via Northern Pacific                           542
Via Portland & Seattle                        389

Saved by Portland & Seattle

Via O.R. & N.                                     542
Via Portland & Seattle                          389

Saved by Portland & Seattle, Distance Saved

Via Northern Pacific                           542
Via Portland & Seattle                        389

Saved by Portland & Seattle

Via O.R. & N.                                     433
Via Portland & Seattle                        389

Saved by Portland & Seattle              44